The engineering question
Is the airflow actually available at the working face adequate for the manpower, diesel equipment and minimum return-air velocity requirements applicable to the tunnel condition?
Inputs
- Tunnel cross-sectional area
- Persons working underground
- Diesel equipment brake horsepower
- Methane-risk condition
- Measured return-air velocity, where available
What the application calculates
- Air requirement for personnel
- Air requirement for diesel equipment
- Air requirement from return-air velocity criteria
- Controlling design airflow
- Required fan delivery after duct efficiency
- Actual airflow from measured velocity × area
- Adequacy percentage and shortfall / surplus
Screening tool, not a substitute for the project ventilation planSite-specific statutory requirements, ventilation layout, leakage, duct condition, auxiliary fans, contaminants, blasting fumes, gas risk and emergency arrangements must be assessed separately by competent persons.